Recovering a Dynamics 365 data migration for a UK public road authority
Brought in when an ambitious migration was going badly — and kept on for four years.
- Client
- UK public road authority
- Sector
- Public sector · road infrastructure
- Engagement
- Contract via two suppliers in turn
- Period
- 2020 – 2024
The situation
In 2020 the authority was part-way through an ambitious migration of data into Dynamics 365 Online, led by its Microsoft partner, and it was going badly. A former colleague from Royal Botanic Gardens, Kew, who had since moved to the authority, recommended Leonard as someone who could put it right.
What we did
- Took over the migration and completed it using SSIS with KingswaySoft
- Stayed on as technical consultant across several road schemes
- Worked near full-time on a major road scheme from 2022, including geospatial data work
- Built an app on the then-new .NET MAUI Blazor Hybrid model
- Worked directly with Microsoft on an image management system over Dataverse, using Custom Pages and Azure Functions
- Carried the knowledge of the system through successive changes of IT support provider
The outcome
The migration was completed, and the work continued for four years under three different contracting arrangements. When the IT support contract changed hands, the incoming provider kept Leonard on.
It ended in 2024, when that scheme was cancelled.
Knowledge of the system is worth keeping
When a contract changes hands, the new supplier inherits the system but not the understanding of it. Here, and again later at a flexible-workspace operator, the incoming supplier's first move was to keep the engineer who already knew it.